Facade Retaining Systems - Home Page
Facade Retaining Systems - Home Page
Facade Retaining Systems - About us
Facade Retaining Systems - Engineering Details
Facade Retaining Systems - Installation Procedure
Facade Retaining Systems - Find a Distributor
Facade Retaining Systems - Photo Gallery
Facade Retaining Systems - FAQs
Facade Retaining Systems - Contact us
Facade Retaining Systems - Video Installation
Facade Retaining Systems - Benefits
Facade Retaining Systems - Online Brochure
Facade Retaining Systems - Products
Facade Retaining Systems - Design Life
Facade Retaining Systems - Power Point Presenation
 
 

Please Contact us


   
 
 
Stylish & Innovative DIY Retaining Wall Systems

Installation Procedure

click here to print this page

The wall has been designed for ease of installation – it’s quick and simple to build.

All components are easily managed by hand. The tools required for the successful installation of the Facade and BRAACE™ Retaining Wall Systems are as follows:

  • String Line
  • Measuring Tape
  • Spirit Level
  • Digging Implement (post hole digger)
  • Screw Gun (drill)

Installation Procedure - Facade Retaining Wall System

Step 1 – Mark out the Wall and Excavate Pier Holes

  • A minimum working area of 700mm is required behind the wall.
  • Set out wall at 1.00 metre centres in desired alignment, and mark post centres.
  • Drill or excavate 300mm diameter hole to required depth (see specification table)
  • Ensure the foundation hole is cleaned of loose soil and debris.

Step 2 – Set the Posts in Concrete

  • Set a string line to the required height (retained height) of the wall, 75mm from the front face of the retaining wall. This will become the alignment and height mark for the front face of the support post.
  • Place concrete in the foundation hole and fill to the top.
  • Push the post into the concrete until the top front edge is level with the string line.
  • Use a spirit level to plum vertical.
  • Leave to set over night.

Installation Procedure - Facade Retaining Wall System

Step 3 – Install Mesh Retaining Panels

  • Apply a bituminous coating to the first 150mm of the post at the base.
  • Starting at the base, place the mesh panel at the rear of the post and secure using the u-clip and type 1 screws. Continue until all panels are secured.
  • Place the waterproof membrane over the mesh, leaving sufficient at the top to allow for stretching during backfilling.
  • Backfill in accordance with the specification.

Installation Procedure - Facade Retaining Wall System

The Installation Procedure - BRAACE™ Retaining Wall System

Step 1 – Mark Out the Wall and Excavate Pier Holes

  • A minimum working area of 700mm is required behind the wall.
  • Set out wall at 1.00 metre centres in desired alignment, and mark post centres.
  • Drill or excavate 300mm diameter hole to required depth (see specification table)
  • Ensure the foundation hole is cleaned of loose soil and debris.


Step 2 – Set the Posts in Concrete

  • Set a string line to the required height (retained height) of the wall, 75mm from the front face of the retaining wall. This will become the alignment and height mark for the front face of the support post.
  • Place concrete in the foundation hole and fill to the top.
  • Push the post into the concrete until the top front edge is level with the string line.
  • Use a spirit level to plum vertical.
  • Leave to set over night.


Step 3 - Install Mesh Retaining Panels and Hebel Facade Panel and Caps

  • Apply a bituminous coating to the first 150mm of the post at the base.
  • Fix the panel connection angles to the post at a height to suit the centre of the panel using the type 1 screws. Panel connection angles are to be used at the ends of the Hebel panels only.

Panel connection angles are to be used at the ends of the Hebel panels only. The type 4 95mm long screws can be fixed into the intermediate support posts

The Installation Procedure - BRAACE Retaining Wall System Screw through Hebel Panel into Fixing Angle using Type 4 95mm Long Tek Screw.

  • Apply a bituminous coating to the first 150mm of the base panel.
  • Starting at the base and ensuring that the panel is sitting firmly on the foundation, or packer, place the panel at the front of the post and screw through the fixing bracket at the rear using the type 2 screws. (Do not over tighten) or place the panel at the front of the post and screw through the panel into the post/fixing bracket using the type 4 screws - continue until all panels are placed.

The Installation Procedure - BRAACE Retaining Wall System 300mm Spacings -  Panel connection angles are to be fixed at the ends of the Hebel panels only.

  • Starting at the base, place the mesh panel at the rear of the post and secure using the u-clip and type 1 screws. Continue until all panels are secured.
  • Place the waterproof membrane over the mesh, leaving sufficient at the top to allow for stretching during backfilling.

 U clips are to be fixed at the top and bottom of the mesh ends only (4 U clips per mesh panel)
The Installation Procedure - BRAACE Retaining Wall System

  • Place the cap using the thin bed adhesive and fix using the type 3 screws. (Do not over tighten)
  • Backfill in accordance with the specification.
  • Finish as desired.

Corner Detail - Internal Corner

  • An additional post is to be installed for 90 degree internal angle for mesh installation.
  • 400mm Spacings - An additional post is to be installed 400mm apart from the corner post to accommodate the mesh for the internal corner.
  • 400mm Spacings - Mesh panels fixed to corner and additional internal corner post.
  • 400mm Spacings - Mesh can be mitre cut to fit the internal angle